Menu

Dudley Street Upgrade

See Dudley Street Upgrade Documents
for YRA analysis of AECOM and Cardno Traffic analyses
and the YRA's 3 EPBC Act submissions.

 

Update July 2022 on signalisation of the intersection of Novar and Kent Streets

YRA Committee members met with Transport Canberra and City Services (TCCS) to raise our concerns with the signalisation plans for the Novar/Kent Streets intersection and specifically the need for a dedicated right turn lane into Yarralumla for traffic travelling south on Adelaide Avenue. YRA also raised other traffic and parking issues in Yarralumla and requested modelling data TCCS has commissioned to model traffic patterns out to 2031.

CORD Civil have been awarded the contract. Works approval from NCA is required before work can commence. Construction will take 18 months.

The ACT Government letterbox dropped a project update newsletter to some households in Yarralumla. You can find a copy here.

Update October 2020

Dudley Street Upgrade and Canberra Brickworks Access Road

Dudley Street photos - October 2020

The Construction Environmental Management Plan was approved at the end of September and number of  pre-construction activities have been undertaken with limit of works pegs surveyed, tree removal signs erected, the archaeological survey of the historical railway alignment and translocation of the Golden Sun Moth larvae has been completed.

Construction work commenced at the beginning of October on the first stage of works that are required for the utility service relocations.  Variable message signs have been installed at both ends of Dudley Street, together with construction warning and vehicle movement signs and site fencing.

The tree removal work was largely complete by mid October and a detour path has been constructed for part of the Uriarra track to enable pedestrians and cyclists to continue to use the track. 

The overhead high voltage electricity line from Cotter Road will also be undergrounded in October, that is the section between the Horse Paddocks and Dudley Street.  Utility service relocations will be undertaken for the water main, gas and telecommunications.  Earthworks activities will commence once this first stage of works has been completed.

In regard to the signalisation of the intersections at the Kent Street Bridge, the plans for the project have not yet been released for community consultation and a contractor has not been appointed.

July 2020

Following an unsuccessful appeal to ACAT by a third party, a contractor has been appointed and all approval
processes have been finalised, so construction is expected to commence in July or August 2020.


The preferred tenderer for the redevelopment of the Canberra Brickworks was announced in June 2017.  The development will provide a maximum of 380 dwellings, various commercial enterprises and re-purposing of the heritage listed buildings.  The development requires the construction of an additional, new, access road that will connect the Brickworks to Dudley Street.  The ACT Government went through the formal legal processes for approval of its plans for the access road and an associated “upgrade” to Dudley Street.  These formal processes were complete, and all necessary approvals were in place by April 2019. These include Commonwealth Government EPBC Act approval for offsets to be used for the destruction of endangered species Golden Sun Moth and Natural Temperate Grasslands habitat, and Works Approval from the National Capital Authority.

Over the two year period the YRA comprehensively engaged with the ACT Government on these proposals and raised many concerns and asked for a number of specific actions – but the plans were not moderated in any way.

Canberra Brickworks proposal 2017

Canberra Brickworks Access Road-Dudley Street Upgrade

Dudley Street Upgrade

The YRA is on record as being opposed to the ACT government’s proposal to upgrade Dudley Street, which we consider to be funds that could be better spent elsewhere. We also object to the Environment Minister’s approval of the proposed environmental impact (the habitat for the critically endangered Golden Sun Moth and Native Temperate Grasslands). The YRA has continued to put pressure on the ACT government to address the issue of congestion at the intersection of Novar Street and Dudley Street before any upgrade to Dudley Street. While we have not stipulated a remedy, we are pleased to hear that the ACT government has started work on designing a solution for the intersection.

Regardless of the final design of the Novar Street/ Dudley Street intersection (which the YRA has not yet seen), we do not believe the Dudley Street upgrade will address the fundamental issue of the increasing traffic on Dudley Street from the Cotter Road and new Molonglo suburbs, much of which is headed towards Deakin, will be addressed until there is construction of the long talked about Mint Interchange.

The Dudley Street upgrade is being proposed as works associated with the development of the Canberra Brickworks Precinct. Dudley Street is already over capacity at morning and afternoon peak times, carrying some 10,000 vehicles per day. At peak times the traffic is bumper to bumper along the full 800 metres of the street with the vast majority of vehicles not seeking to  access Yarralumla but using Dudley Street to access West Deakin. An additional 2,500 vehicle movements per day are forecast for Dudley Street once the Canberra Brickworks Precinct is activated, but the upgrade, while bringing the road up to current standards, does not provide any additional capacity as it remains one lane in each direction.

New Canberra Brickworks Access Road

The YRA is on record as supporting a road from Dudley Street (or the Cotter Road) that directly connects and will be the main entry point to the Canberra Brickworks Precinct. We also acknowledge that the ACT Government has confirmed that this new Brickworks Access Road will only enable access to the Canberra Brickworks Precinct with no direct link to existing streets in Yarralumla.

This is based on the need to avoid the congestion that would arise if the main entry were from Bentham or Denman Streets or if it were possible to access these streets from the new Brickworks Access Road.

The YRA is on record as supporting the construction of this road ahead of the development of the Canberra Brickworks Precinct to ensure most construction vehicles and equipment enter the site from this road. However, the YRA objects to two aspects of the design:

  1. A roundabout instead of lights at the intersection of the New Brickworks Access Road and Dudley Street.
  2. The priority given to vehicles over pedestrians and cyclists where the Old Uriarra Track intersects with the Access Road

Pedal Power and other community groups have asserted that traffic lights would be better for pedestrians and cyclists. Traffic lights would not take up as much space thereby reducing the environmental impact. We doubt the veracity of traffic projections and anticipate there will be congestion in the vicinity of the roundabout.

The YRA and other community groups have for many years advocated for the prioritisation of pedestrians and cyclists over vehicles. Suggestions for a bridge or tunnel were rejected due to their costs, yet no such rationale has been given for rejecting a wombat crossing (raised pavement) that would signal to drivers that they need to slow for pedestrians and cyclists. This remains a safety issue and the YRA will push for retrofitting the road if such plans are not incorporated in the original design.

Golden Sun Moth Habitat and Natural Temperate Grasslands

The area in the vicinity of the Yarralumla Uniting Church and in the open areas that extend to Dunrossil Drive are home to the critically endangered Golden Sun Moth and Natural Temperate Grasslands. The area has been subject to numerous surveys over many years. Based on surveys commissioned by the ACT Government, the Golden Sun Moth habitat in this area appears to have increased almost 3‐fold in 3 years, from 2.5 ha in 2014 to 7.39 ha in 2017. The area of Natural Temperate Grassland is reportedly 0.75 ha.

Golden Sun Moth Brickworks

Golden Sun Moth Habitat - Canberra Brickworks Precinct

The YRA is disappointed that the Environment Minister chose to approve an application from the ACT Government to upgrade Dudley Street and build a new Brickworks Access Road that will together destroy 43% of the Golden Sun Moth habitat and 17% of the Natural Temperate Grassland.

Although an offset site has been approved, this is not a 100% offset as statutorily required. The obligation placed on the ACT Government for the shortfall is one year of monitoring at the existing site with no further remediation required.

EPBC Act Referrals on Canberra Brickworks and Dudley Street Upgrade/Access Road

CANBERRA BRICKWORKS DEVELOPMENT on Residential Development/Blocks 1, 7, and 20; Section 102 Yarralumla, ACT/Australian Capital Territory/The Canberra Brickworks Precinct, Blocks 1, 7, and 20 Section 102, Yarralumla, ACT- Reference number 2017/8074

CMTEDD ACT PROCUREMENT/Transport - Land/Yarralumla, Section 94 Block 3/Australian Capital Territory/Canberra Brickworks Precinct access road and Dudley Street upgrade, ACT2017/8072

See Dudley Street Upgrade Documents for YRA analysis of AECOM and Cardno Traffic analyses and the YRAs 3 EPBC Actn submissions.